DAY TWO


Once the perimeter berms are in place they need to be seeded and mulched with straw.



And then a check dam added to filter the run-off silt.



A construction entrance made of #1 VDOT stone is added to help with control of mud not leaving the site on vehicle and dump truck tires.

Once all of this has been installed, the county inspector is notified and he will come inspect and issue an Erosion & Sediment Control Report. At that point, the real work begins.